ELECTRICITY PROJECT PT. CATUR YASA

 

No

PROJECT NAME

PERIOD

PROJECT VALUE

OWNER

SCOPE

PARTNER

REMARK

 

1

 

Gassification & Rehabilitation  Project of Frame -7 GE Gas Turbine

 

 

1994-1995

 

Rp.74,792,890,000.00

 

PT.PLN (Persero)

 

 

P-C

 

Sub Con PT. Triharsa

·          Design Engineering

·          Overall rehabilitation & Changing Single to dual Fuel System of 4 Unit 50 MW Turbine, compressor, Cooler, auxiliaries equipment etc

·          Piping Work

·          Start Up & Commissioning

 

2

 

Rehabilitation of PLTU Belawan Unit 1 & 2

 

 

1993

 

Rp.82.425.866.809.00

 

PT.PLN (Persero)

 

 

E-P-C

 

Main

 

Rehabilitation PLTU  Belawan Unit 1 & 2

 

 

 

 

 


Project Name

:

Gassification & Rehabilitation Project of Frame-7 GE Gas Turbine Unit 4,5,6&7 PLTG Priok

Year of Completion

:

1994 – 1995

Owner

:

PT. PLN  (Persero)

Location

:

Tanjung Priok, Jakarta

 

Project Description   :

 

4 x 50 MW Frame-7 GE Gas Turbine of PLTG Priok is under control of PLN Priok Sector and one of Power Plants which generate power to be distributed to West Side of Java PT. Catur Yasa was responsible for changing single to dual fuel system and rehabilitation/recondition of the turbine and other parts.


Project Name

:

Rehabilitation of PLTU Belawan Unit 1 & 2

Year of Completion

:

1993

Owner

:

State Electricity Company (PLN)

Location

:

Belawan North Sumatera

Project Description   :

 

Design & Engineering for Overall rehabilitation  of 2 unit 65 MW Oil Fired Steam Turbine Boilers, Condensors, Auxiliaries, Electrical, Etc including Start up & Commissioning

 

 
  • An Image Slideshow
  • An Image Slideshow
  • An Image Slideshow
  • An Image Slideshow
  • An Image Slideshow
  • An Image Slideshow
  • An Image Slideshow
  • An Image Slideshow
  • An Image Slideshow
  • An Image Slideshow
  • An Image Slideshow
  • An Image Slideshow
  • An Image Slideshow
  • An Image Slideshow
  • An Image Slideshow
  • An Image Slideshow